All the Alstom masters (~500) installed in the LHC will be replaced by the new design in 2019, at the beginning of CERN's Long Shutdown 2.
Since 2016 we have replaced lab installations, of some of the most
critical LHC users, as listed in the table below.
| Application| *Midration date *|
|Cryogenics| 06-2016 |
|Radiation Monitoring| 09-2016 |
|Quench Protection System| 10-2016 |
|Function Generator Controller| 02-2017 |
|Beam Instrumentation| 03-2017 |
Currently, there are also few installations in operation:
| Application| *Facility |Date *|
|Rad-Mon| CHARM| 04-2017 |
|Rad-Mon| AWAKE| 06-2017 |