... | ... | @@ -97,7 +97,7 @@ prospects*](https://www.researchgate.net/publication/325285614_Analog-to-digital |
|
|
|----|----|
|
|
|
|04-05-2018|Start working on project. First prototype design expected in second half 2019.|
|
|
|
|20-12-2019|[First prototype series evaluated](https://edms.cern.ch/ui/file/2302118/1/HPM7177_Evaluation_docx_cpdf.pdf).|
|
|
|
|27-01-2020| <POSTPONED DUE TO COVID-19> Characterization tests will be done in [PTB, the National Metrology Institute of Germany. ](https://www.ptb.de/cms/en.html)|
|
|
|
|27-01-2020| *POSTPONED DUE TO COVID-19.* Characterization tests will be done in [PTB, the National Metrology Institute of Germany. ](https://www.ptb.de/cms/en.html)|
|
|
|
|19-02-2020| Added link to [13.02.2020 Hi Lumi TCC talk](https://edms.cern.ch/ui/file/2323037/1/tcc_1302_beev.pdf)
|
|
|
|03-03-2020| Added [datasheets of Vishay resistor arrays](https://ohwr.org/project/opt-adc-10k-32b-1cha/wikis/datasheets)
|
|
|
|11-03-2020| [Block diagram](https://ohwr.org/project/opt-adc-10k-32b-1cha/wikis/uploads/05d1ae1b68ece422ee1ddac75718e38c/Block_diagram.png) added.
|
... | ... | |