WP1 Scope, objectives, resources, budget definition | Strukton solution evaluation
Description
The work package 1 includes the
- risk analysis of the WorldFIP master situation in communication with all the users
- understanding the WorldFIP master requirements
- study of the WorldFIP master Strukton design
- study of the possibility to use an FMC solution
The deliverables are
- a document describing the
- reasons for the development
- work packages
- for the understanding of the available solutions and a good
estimation of the project duration, it is decided to
build a very draft prototype with a SPEC and an existing FMC mezzanine (with necessary modifications) that performs very basic data exchange;
data is written in a memory and is "played" in the WorldFIP bus; the nanoFIP client node replies
The estimated duration is
- Fourteen manweeks
Outcome
- Document describing the technical choices made for the masterFIP HDL design - pdf
E.Gousiou, July 2014